Construction Law of the Peoples Republic of China (1)

来源:中国法律法规大全  点击数:  更新时间:2005-9-18 19:59:03 

 
ow the threshold value set by the competent
construction administrative department under the State Council.
Construction projects which have obtained approval of work start reports
in accordance with the power limits and procedure stipulated by the
State Council are no longer required to apply for construction licenses.
Article 8 The following conditions are required for the application of
construction licenses:
(1) Having gone through the approval formalities for construction
project land use;
(2) Construction projects within urban planned districts have obtained
licenses of planning;
(3) Where demolition and relocation are necessary, the progress of
demolition and relocation comply with the requirements of construction;
(4) Constructing enterprises for the projects have been chosen;
(5) Working drawings and technical data are available to meet the need
of construction;
(6) Specific measures are available for ensuring the quality and
security of construction;
(7) Funds of construction are available;
(8)  Other conditions as stipulated by laws  and  administrative
regulations.
The competent construction administrative departments shall  issue
construction licenses to qualified applicants within 15 days from the
date of receipt of applications.
Article 9 Units in charge of construction should start to build the
projects within three months since obtaining construction licenses. If
work cannot start on schedule, applications should be filed to the
license issuing agencies for delay, which shall only be permitted twice
in maximum for each case, each permission of delay covering a maximum
period of three months. In cases of those projects that neither start on
schedule nor apply for delay or exceed the period of permitted delay,
the validity of the working licenses automatically expires.
Article 10 For projects under construction that come to a halt due to
some reasons, the constructing units should report to the license
issuing agencies within one month from the stoppage of construction and
should also well maintain and manage the construction projects in
accordance with provisions.
When construction work resumes, reports should be filed with the license
issuing agencies; Before the resumption of work on construction projects
which have stopped for over one year, units in charge of construction
shall apply to the license issuing agencies for verification of their
working licenses.
Article 11 For construction projects with approval of work-start reports
in light of the relevant provisions of the State Council which fail to
start construction on schedule or suspend the construction work due to
certain reasons, the constructors should report the cases timely to the
approving authorities. If the p

上一页  [1] [2] [3] [4] [5] 下一页

 


相关法律法规文章
Construction Law of the Peoples Republic of China (3)…
Construction Law of the Peoples Republic of China (2)…
最新热点
推荐法律 Individual Income Tax Law of t…
推荐法律 Labour Law of the Peoples Repu…
推荐法律 Law of the Peoples Republic of…
推荐法律 Criminal Law of the Peoples Re…
推荐法律 Criminal Law of the Peoples Re…
推荐法律 Economic Contract Law of the P…
推荐法律 Company Law of the Peoples Rep…
推荐法律 Labour Law of the Peoples Repu…
推荐法律 Construction Law of the People…
推荐法律 Company Law of the Peoples Rep…
推荐法律 Individual Income Tax Law of t…
推荐法律 Response of the Supreme People…
推荐法律 Criminal Procedure Law of the …
推荐法律 Detailed Rules and Regulations…
推荐法律 Economic Contract Law of the P…
Copyright © 2001-2010 chnlaw.net All Rights Reserved 中国法律法规大全 版权所有
声明:本站法律法规仅供学术研究参考,请与正式出版物或发文原件核对后使用。